Stephen J. Christian & Associates, P.C.

Home

Services

Projects

Bridge Design

Road Design

Bridge Inspection

Drainage

Misc. Structural Design

Pedestrian Facilities

Civil/Site

Construction Observation

Land Surveying

Awards for Design

News

Indiana Weather

About SJCA

Professional Affiliations

Contact Us

Employment

FTP Login

COMMITTED TO CIVIL ENGINEERING EXCELLENCE SINCE 1998

West 34th Street over I-465 Indianapolis

This project included the design of an overpass bridge and street approaches for the Accelerate 465 project. The bridge is a two span prestressed concrete bridge with approximately 0.5 mile of urban street reconstruction. Some of the unique features of this project are MSE walls for the entire project, monuments at bridge and context sensitive solutions (CSS) approach applied to design components such as retaining walls, monuments, sidewalks, parapets and ornamental railing. The project included new enclosed storm drainage systems. The construction cost for this project was approximately 5.5 million dollars

US 231 over O’Neall Ditch in Tippecanoe Co.

The design of this bridge replacement project was completed by SJCA for Crawfordsville District in 2004. The existing bridge was replaced with a single span prestressed concrete box beam bridge. The project included 900 feet of road reconstruction plus 700’ of incidental construction at the north end of the project to upgrade superelevation at an existing horizontal curve. Traffic was maintained throughout the construction period utilizing a temporary run around. A low bid of $959,966.05 was received for the project. The final construction cost of $966,448.15 was within 0.7% of the bid amount demonstrating the high quality of the construction documents.

SR 18 over Tributry to Mud Creek in Benton County

The design of this bridge replacement project was completed by SJCA for Crawfordsville District in 2001. The existing bridgewas replaced with a three span continuous reinforced concreteslab bridge. Approximately 1700 feet of road realignment was included to upgrade sight distance at an existing horizontal curve. The construction cost for the project was $636,000

SR 28 over Foster Branch in Warren County

The design of this bridge replacement project was completed by SJCA for Crawfordsville District in 2004. The existing bridge was replaced with a single span three-sided precast concrete bridge. Approximately 700’ of roadway reconstruction was included with this project. Coordination with the State of Illinois was required for the roadway detour. The construction cost for the project was $476,000.

West 46th Street over I-465 Indianapolis

This project included the design of an overpass bridge and street approaches for the Accelerate 465 project. The bridge is a two span prestressed concrete bridge with approximately 0.5 mile of urban street reconstruction. Some of the unique features of this project are MSE walls for the entire project, monuments at bridge and context sensitive solutions (CSS) approach applied to design components such as retaining walls, monuments, sidewalks, parapets and ornamental railing. The project included new enclosed storm drainage systems. The construction cost for this project was approximately 5 million dollars

West 21st Street over I-465 Indianapolis

This ACEC Honor Award Winning project included the desing of an overpass bridge and street approaches for the Accelerate 465 project. The 21st Street Bridge is the first bridge in Indiana to utilize a prestressed concrete U-beam. This beam type has been previously used by DOTs in Florida, Texas, Colorado, and Washington. The Indiana U-beam details provided improvements from previous designs by utilizing draped strands instead of debonded strands to improve beam performance in shear, using steel internal diaphragms to reduce weight and simplify internal formwork, and provided inspection access inside the box. The advantages of the U-beam compared to other Indiana standard beams are reduced structure depth, improved aesthetics, and more efficient use of materials. The beam details were developed as typical prestressed concrete members that could be designed utilizing common prestressed concrete bridge design software. Approximately 0.4 mile of urban street reconstruction was included in the project. The roadway approaches consisted of a curb and gutter section with enclosed drainage and MSE walls to minimize right of way impacts. The construction cost for the project was $7,050,000.

Hanna Avenue over I-465 Indianapolis This project included the design of a overpass bridge and street approaches for the Accelerate 465 project. The bridge is a two span continuous prestreessed concrete Bulb-T bridge with approximately 0.3 mile of urban street reconstruction. The project included new enclosde storm drainage systems. The project also included resurfacing a portion of Kolman Road that was used as a local detour route during construction of the project. A low bid of $3,588,760.00 was received for the project.

SR 218 over Branch of Pipe Creek in Miami County

The existing structure was replaced with a single span three-sided precast concrete structure. The project included 1200 feet of roadway reconstruction including reconstruction to improve the superelevation at two adjacent horizontal curves. A low bid of 482,782.64 was received on the project. All five bids received were within 8% of the low bid demonstrating the high quality of the plans and specifications.

Wayne Bridge 184 on Dingle Road over Morgan Creek

The existing structure was replaced with a continuous three span reinforced concrete slab bridge. The project included 500 feet of approach roadway reconstruction. The construction cost was $202,000. SJCA’s services including a subconsultant prepared survey, bridge and roadway design, permit applications, utility coordination, and right of way engineering. This was SJCA’s first bridge replacement project design completed.

US 421 over Fraser Ditch in White County

The existing structure was replaced with a continuous three span reinforced concrete slab bridge. The project consisted of 900 feet of road reconstruction that included lowering the roadway profile to improve intersection sight distance at county road immediately north of the structure. The plans included details for maintaining traffic with temporary traffic signals throughout the construction period. A low bid of 767,700.26 was received on the project.

SR 110 over Eddy Creek in Marshall & Fulton Counties

The existing structure consisted of multiple pipe arches that had considerable settlement due to poor soil conditions within the project area. The design solution consisted of providing a single span prestressed concrete I beam bridge on piles to provide support below the layer of unsuitable soils. The design solution also included using a geogrid and light weight engineered fill for approach reconstruction in lieu of excavating and replacing the unsuitable soils. This provided an economical solution consistent with the classification and traffic volume of the roadway. A low bid of 1,096,000 was received on the project.

US 231 over Falls Branch in Putnam County

The existing structure was replaced with a single span three-sided precast concrete structure. The project length was 600 feet and included designing to eliminate impacts to an adjacent historic property. The plans included details for maintaining traffic with temporary traffic signals throughout the construction period. A low bid of 623,400.35 was received on the project

SR 3 over Graham Creek in Jennings County The existing structure was replaced with a three span continuous composite steel beam structure. A 3500 foot length of roadway was re-aligned as part of the project. Two state route intersections and numerous drives were also reconstructed. Traffic was maintained on the existing alignment with temporary connections supplied at the intersections and project limits. A low bid of $3,076,354.83 was received on the project.
Hendricks County Bridge 34 on CR 700 North over School Branch

The existing area is within the flood plain and the bridge and roadway approaches were designed to pass a ten year discharge through the bridge and allow bridge and roadway overtopping for more extreme flooding events. A variable depth three span continuous reinforced concrete slab bridge was the selected structure type. The shallow superstructure minimized the grade raise of the roadway approaches to allow for over the road flow for extreme flood events. This design concept provided significant savings in construction cost compared to the longer bridge and roadway approaches that would have been required to pass a hundred year flood through the structure. The construction cost for this project is $391,000. The three lowest bids were within 3%. This is an indication of the clarity of plans and specifications and that each of the three bidders had a high level of confidence in the documents when preparing their bids.

SR 10 over Myers Ditch in Marshall County The design for this bridge replacement project in LaPorte District was completed by SJCA in 2004. The existing structure was replaced with a continuous three span reinforced concrete slab bridge. The project consisted of 700 feet of road reconstruction including pavement replacement, shoulder construction, and guardrail installation. SJCA also prepared permit applications for the “Rule 5” permit and a regional general permit for IDEM and the Corps of Engineers. The construction cost for this project was approximately $425,000.
I-465 over College Avenue in Marion County

The design of these bridge replacements was completed by SJCA in 2009 as a part of the I-465/I-69 Added Travel Lanes Project. The new bridges increased the travel lanes from three lanes to five lanes in each direction. The replacement structures were single span prestressed concrete I-beam structures with integral end bents behind MSE wall abutments. The structures were built to the long chord of a horizontal curve. Form liners and tinted surface seal were included to enhance the visual effect in accordance with the CSS features designed into the project. The construction cost for this portion of the project was approximately $2,600,000

SR 10 over Wolf Creek in Marshall County The design for this bridge replacement project in LaPorte District was completed by SJCA in 2004. The existing structure was replaced with a continuous three span reinforced concrete slab bridge. The project consisted of 800 feet of road reconstruction including pavement replacement, shoulder construction, and guardrail installation. The design included a review of horizontal sight distance for an adjacent intersection with a county road. SJCA also prepared permit applications for the “Rule 5” permit and a regional general permit for IDEM and the Corps of Engineers. The construction cost for this project was approximately $415,000.
SR 32 over I-74 in Montgomery Co. The design of this bridge rehabilitation project was completed by SJCA for Crawfordsville District in 2006. The rehabilitation of this structure included a new deck and shoulder widening for the existing four span steel beam bridges. The superstructure construction included fatigue retrofits at cover plates and adding shear connector to provide a composite structure. The structural steel was jacked, supported, and bearings replaced to increase the vertical clearance over I-74. Traffic was maintained throughout the construction period using temporary traffic signals. The construction cost for this project was $1,800,000.
36-61-4384B on US 36 over Troutmans Branch in Parke Co. The design of this bridge rehabilitation project was completed by SJCA for Crawfordsville District in 2006. The rehabilitation of this structure included a new deck and replacing the existing concrete end spans with steel beams. Shear connector were added to provide a composite structure. The steel beam end spans were spliced to the existing structural steel. This plus the use of semi-integral end bents eliminated all expansion joints for the bridge. Traffic was maintained throughout the construction period using temporary traffic signals. The construction cost for this project was $1,260,000.
Prospect/Morris Streets over SB I-65 and Ramp 7N-S This project consisted of deck reconstruction, overlay and rail replacement for an existing 2 span bridge on Prospect/Morris Streets in Indianapolis over SB I-65 and Ramp 7N-S. The existing sidewalks and copings were removed and replaced and the existing aluminum bridge rail replaced with concrete rail. The project also included mudwall reconstruction and approach slab replacement. The partial replacement of the outsides of the bridge in combination with the bridge deck overlay provided a cost effective solution compared to complete deck replacement. A low bid of $668,120 was received on the project compared to our engineer’s estimate of $705,205.
Cyntheanne Road over I-69 This project consisted of deck reconstruction, overlay and rail replacement for an existing 5 span bridge on Cyntheanne Road over I-69 in Hamilton County. The existing aluminum bridge rail and portions of the curb were removed and replaced with concrete barrier rail doweled into the existing deck. The project also included mudwall reconstruction, approach slab replacement, new asphalt shoulders and guardrail. Our services included coordination with Hamilton Southeastern Schools to reduce impacts to school bus routes during the road closure period. A low bid of $412,259 was received on the project compared to our engineer’s estimate of $438,154.
Georgetown Road over I-65 and Little Eagle Creek in Marion Co.

This project involved a superstructure replacement and widening over an interstate and an adjacent stream crossing. The existing five span reinforced concrete girder and continuous plate girder superstructure was replaced with a new four span continuous composite steel plate girder superstructure. A full height concrete abutment was utilized to eliminate an existing end span. The structure was widened from two lanes to five lanes plus a pedestrian/bicycle facility. SJCA’s design solution saved significant substructure reconstruction costs. The original design required only minimal reinforcement in the existing interior bents. SJCA investigated multiple design scenarios and provided a solution enabling the existing interior bents to be incorporated into the widened structure. The construction cost for this project was $3,850,000.

US 41 over N & S Railroad in Newton County.

The design of these railroad grade separation structures was completed by SJCA in 2003. The project consisted of design of a new five span continuous composite steel beam superstructures and substructure widening to obtain required shoulder widths for the twin structures. The project required 1300 feet of four lane divided roadway reconstruction to raise the profile grade and provide the required minimum vertical clearance over the railroad tracks. This project demonstrates SJCA’s ability to “design to cost”. Our original cost estimate prepared with the Bridge Inspection Report was $2,875,000. A low bid of $2,239,996.48 was received compared to the Engineer’s Estimate of $2,661,911.21. The final construction cost at project completion was $2,303,723.85. The final construction cost was within 3% of the bid value demonstrating the high quality of the final construction documents.

SR 2 over Cedar Creek in Lake County.

The design for this major bridge rehabilitation project was completed by SJCA in 2005. The structure is in the middle of a “Y” shaped intersection in downtown Lowell. SR 2 is along a horizontal curve through the south side of the structure and Washington Street is on a tangent through the north side of the structure. The structure is a single span @ 28’ perpendicular to the abutments having skews of 11ş left at SR 2 and 53ş 42’ left at Washington Street. The project included complete superstructure replacement. The tight constraints within the “Y’ shaped intersection would have typically been constructed in three or more phases. Cost and time savings were achieved by developing a scheme that provided temporary structure support details without the use of false work to reduce the area separating traffic from construction and provide for construction of the project in two phases. Two superstructure types were utilized to further reduce the construction period for each phase. The majority of the bridge consists of composite prestressed concrete box beams eliminating the need for false work. A pie shaped segment at the north side of the bridge is a reinforced concrete slab. New semi-fixed integral end diaphragms were fastened to the existing vertical abutment walls eliminating all expansion joints on the structure. This project had very complex geometry issues and required a structure layout sheet for specifying beam locations and curved coping offsets and a spot elevation sheet. This project also demonstrates SJCA’s experience in “designing to cost.” The cost estimate prepared for the Bridge Inspection Report indicated an anticipated construction cost of $810,000. SJCA’s cost estimate submitted with the tracings was $762,802.16 and a low bid of $754.639.44 was received on the project.

SR 55 and SR 26 over Big Pine Creek in Warren County.

The design for this project, completed in 2006, consisted of replacing the existing superstructure with a three span continuous composite prestressed concrete box beam superstructure. The project had several unique items compared to typical superstructure replacement. Big Pine Creek is considered an exceptional use stream and expansion joints and deck drains were eliminated from the structure to prevent bridge deck drainage from discharging directly into the stream. The new superstructure was also designed to require minimal reconstruction to the substructure units. Permitting requirements for construction of the project were more involved than normal due to the exception use designation. A sag vertical curve immediately north of the bridge was re-designed to meet sight distance criteria. A review of the intersection sight distance at the SR 26 and SR 55 intersection north of the bridge was also performed. This project demonstrates SJCA’s ability to “design to cost”. Our original cost estimate prepared with the Bridge Inspection Report was $580,000. A low bid of $599,951.44 was received compared to the Engineer’s Estimate of $626,751.97. The final construction cost at project completion was $588,807.09.

I-74-95-4210B on Franklin Road over I-74 in Marion County

     This project included superstructure replacement for this five span overpass bridge. The existing reinforced concrete girder superstructure was replaced with a new five span continuous composite prestressed concrete I-beam superstructure. The construction plans included details for temporary lane closures as required on I-74. The project included coordination with an upcoming interstate rehabilitation project for compatibility with new profile grades. The construction cost for the project was $730,000.


CR 400 North over I-69 in Steuben County.

The design for this major bridge rehabilitation project in Fort Wayne District was completed by SJCA in 2004. The structure was converted from an existing 4 span bridge to 2 spans of 116’-6” and 117’-9”. The structure is built on a tangent and is square. The design included widening to provide a bicycle pathway and complete superstructure replacement with continuous composite steel plate girders. The bridge is located on a dead end road and closing the bridge was not an option since the route served as the only access for a residential area. The maintenance of traffic and structure details provided for maintaining traffic over the structure at all times overcoming the tight constraints of the existing narrow bridge width and the change in profile grade without the necessity of temporary bridge widening. Utilizing the center portion of the existing hammerhead pier and widening the outsides to provide a solid stem pier contributed to maintaining one lane of traffic throughout the project by eliminating the need for major excavation and pile driving near the construction joint.

Marion 1001F on 62nd Street over Guion Creek Indianpolis

This federally funded LPA project involved design of a superstructure replacement and widening for a single span bridge on West 62nd Street over Guion Creek in Indianapolis. The new superstructure is a single span spread prestressed concrete box beam. There were two street intersections reconstructed as part of the project. The roadway was widened to a three lane section. A pedestrian/bicycle facility was included on the south side of the bridge. The north shoulder width was increased beyond the minimum requirement to provide the required intersection sight distance at the Rodebaugh Road intersection. The Engineer’s Estimate was $1,256,555.00 and a low bid of $1,162,149.06 was received on the project. In addition to bridge rehabilitation design, this project demonstrates SJCA’s experience in intersection design and designing the bridge to accommodate intersection sight distance

Whiteland Road over I-465 in Johnson County.

     The rehabilitation of Structure I-65-94-5536A on Whiteland Road over I-65 was originally programmed for 2003 construction. The schedule was accelerated to complete construction of the project during the summer of 2002 prior to the opening of a new truck stop. The inspection report, preliminary plans, final plans, and tracings were all completed from January 11, 2002 to March 27, 2002 to enable the project to be let in July. Our design also included elements to shorten the construction period such as utilizing metal bridge rail to eliminate curing times associated with typical poured in place concrete bridge rails. A low bid of $348,502.68 was received compared to the Engineer’s Estimate of $461,792.46. The final construction cost at project completion was $350,744.48. The final construction cost was within 0.7% of the bid value demonstrating the high quality of the final construction documents

Hendricks County Bridge 188

This project consists of the rehabilitation of Bridge 188 carrying CR 0 over Branch of Mud Creek. The existing single span steel superstructure was replaced with a prestressed concrete superstructure. The existing abutments were reconstructed and wingwalls added at two corners to allow for increasing the clear roadway width approximately four feet. Utilizing the existing substructure resulted in significant cost savings compared to structure replacement. Services included the topographic survey, design, and right of way engineering. A low bid of $163,958.92 was received compared to the Engineer’s Estimate of $265,978.28. The final construction cost at project completion was $170,201.64 which included costs for unforeseen conditions. The final construction cost was within 3.8% of the bid value demonstrating the high quality of the final construction documents.

Structure No. 14-37-6650A over Oliver Ditch

     The design for this bridge rehabilitation project in LaPorte District was completed by SJCA in 2003. The project consisted of deck reconstruction, overlay and rail replacement for an existing 3 span concrete slab bridge in Jasper County. The coping and outside portions of the variable depth concrete superstructure were replaced and concrete barrier rail constructed. The project also included approach slab replacement, new asphalt shoulders and guardrail. The plans included details for maintaining traffic with temporary traffic signals throughout the construction period. The design included a review of horizontal sight distance for an adjacent intersection with a county road. SJCA also prepared permit applications for IDNR construction in a floodway permit and a regional general permit for IDEM and the Corps of Engineers. A low bid of $441,954.35was received on the project.


Structure No. 031-49-4448B on US 31 over I-465 and Lick Creek in Marion County.

     SJCA completed the design for this major bridge rehabilitation project in less than nine months. We started the design in July of 2008 and submitted the tracings in March of 2009. This accelerated schedule allowed INDOT to take advantage of the phase 1 economic recovery funds. The project consists of superstructure replacement for an existing seven span bridge. A new steel beam superstructure was selected in order to minimize the dead loads and utilize the existing substructure units. The structure also consists of three superstructure units to minimize forces exerted on the substructure units. This design concept also allowed for a different beam size and spacing for the middle three spans resulting in a significant decrease in the weight and cost of structural steel required. The expansion joints at the existing end bents were eliminated by providing semi-integral end bents. The caps and columns of the interior bents were also replaced. The existing bridge width was too narrow to maintain two lanes of traffic in each direction on this heavily traveled arterial. The traffic volume on the northbound lane is significantly higher than the southbound lane during the AM peak with the opposite condition during the PM peak. Movable barrier was utilized to maintain two lanes of traffic in the peak direction and avoid temporary over-widening of the bridge to maintain two lanes of traffic in each direction. This concept saved thousands of dollars by avoiding substructure widening. The construction cost of this project is $4,016,000.


I-69 over Lake George Road in Steuben County.

The design for this major bridge rehabilitation project in Fort Wayne District was completed by SJCA in 2004. The project included superstructure replacement and widening for twin three span bridges on I-69 over Lake George Road. A continuous steel beam superstructure was utilized to maintain the existing vertical alignment. This provided savings in the construction cost by minimizing the approach reconstruction which consisted of approach slab replacement and HMA wedges. The structure widening was relatively small and savings were achieved by reconstructing interior piers with longer cantilevers to accommodate the new superstructure width. The end bents were widened without driving additional piling by providing an increase in the cap overhang. The construction cost for this project was $2,400,000.

US 41 over K. B. & S. Railroad and E.B. US 52 in Benton Co.

The design of this bridge rehabilitation project was completed by SJCA for Crawfordsville District in 2006. The rehabilitation of these structures included a new deck and shoulder widening for the existing four span steel beam bridges. The superstructure construction included fatigue retrofits at cover plates and adding shear connector to provide a composite structure. The structural steel was jacked, supported, and steel bearings replaced with elastomeric bearings. Additional piles were driven and the end bents widened to accommodate the additional structure width. The footings, collision wall and cap were extended, and additional columns added at the shoulder widened areas. Interior columns with deterioration were repaired by installing fiber wrap which resulted in significant construction cost savings by eliminating the need for replacing the existing caps. Traffic was maintained throughout the construction period using temporary crossovers. The construction cost for this project was $2,900,000.

I-465 over Carmel Creek in Marion Co.

The design of this bridge rehabilitation was completed by SJCA in 2009 as a part of the I-465/I-69 Added Travel Lanes Project. The rehabilitation of these structures included a new deck and widening at the median and outside shoulders for the existing three span steel beam bridges. The widening increased the travel lanes from three lanes to five lanes in each direction. The superstructure construction included adding shear connectors to provide a composite structure. The structural steel was jacked, supported, and steel bearings replaced with elastomeric bearings. Additional piles were driven and the end bents widened to accommodate the additional structure width. Semi-integral construction at the end bents eliminated all expansion joints from the bridges. The pier stems extended on footing founded on piles. The construction cost for this portion of the project was approximately $2,200,000.